ANALYSIS OF PRE-PROJECT DATA FOR FLEXIBLE OPPORTUNITIES ON ROAD PROJECTS IN NORWAY

DOI: 10.7708/ijtte2022.12(3).09


12 / 3 / 404-418 Pages

Author(s)

Rouzbeh Shabani - Norwegian University of Science and Technology, Department of civil and environmental engineering, Norway -

Andrei Marsov - Norwegian University of Science and Technology, Department of civil and environmental engineering, Norway -

Olav Torp - Norwegian University of Science and Technology, Department of civil and environmental engineering, Norway -

Nils Olsson - Norwegian University of Science and Technology, Department of mechanical engineering and production, Norway -


Abstract

This paper focused on pre-defined reduction lists as one of the flexibility options in large investment road projects and attempted to obtain knowledge about reduction lists and their relationship with uncertainty. As information in the front end of projects is scarce having historical data about general reductions could be informative for new projects which helps consultants in identifying reduction possibilities. Furthermore, literature is currently lacking on the relationship between reductions and uncertainty. Knowing this relation leads to the use of flexibility for better uncertainty management through investigating more reductions as well as to understand the perspective of consultants about potential reductions in the sample of transport road projects. This study was based on qualitative and quantitative evaluation of 80 transport road projects. Analysis of reduction types showed that there are similar reductions to those found in previous studies. Uncertainty level had a statistical relationship with the changes in reductions. Data from these projects could give good direction to decision-makers at the portfolio level on the value of reductions and their relation with estimated uncertainties. However, reduction lists are not the only way to tackle extra costs and contingencies can be exploited for better cost management in projects and to help uncover new opportunities.


Download Article

Number of downloads: 233


References:

Awe, O.A.; Church, E.M. 2020. Project flexibility and creativity: the moderating role of training utility, Management Decision 59(9): 2077-2100.

 

Cantarelli, C.C.; van Wee, B.; Molin, E.J.E.; Flyvbjerg, B. 2012. Different cost performance: Different determinants?. The case of cost overruns in Dutch transport infrastructure projects, Transport Policy 22: 88–95.

 

Charles, S.P.R.; Wanigarathna, N.; Sherratt, F. 2015. Construction project change: Investigating cost and benefits. In Proceedings of the 31st Annual Association of Researchers in Construction Management Conference, ARCOM 2015, 833–842.

 

Chevroulet, T.; Giorgi, L.; Reynaud, C. 2012. A New Paradigm for the Assessment of High Speed Rail Projects and How to Contain Cost Overruns: Lessons from the EVA-TREN Project, SSRN Electronic Journal, 15 p. Available from Internet: https://doi.org/10.2139/ssrn.1910565.

 

Cui, Y.; Olsson, N.O.E. 2009. Project flexibility in practice: An empirical study of reduction lists in large governmental projects, International Journal of Project Management 27(5): 447–455.

 

Evans, S.; Bahrami, H. 2020. Super-Flexibility in Practice: Insights from a Crisis, Global Journal of Flexible Systems Management 21(3): 207–214.

 

Flyvbjerg, B.; Skamris Holm, M.K.; Buhl, Sø.L. 2004. What causes cost overrun in transport infrastructure projects?, Transport Reviews 24(1): 3–18.

 

FTA. 2016. Value Engineering on Transit Projects. Available from Internet: https://www.transit.dot.gov/regulations-and-guidance/value-engineering-ve-transit-projects.

 

Gray, D.E. 2014. Doing Research in the Real World. SAGE. 26 p.

 

Günsel, A.; Açikgšz, A.; Tükel, A.; Öğüt, E. 2012. The Role Of Flexibility On Software Development Performance: An Empirical Study On Software Development Teams, Procedia - Social and Behavioral Sciences 58: 853–860.

 

Hillson, D. 2002. Extending the risk process to manage opportunities, International Journal of Project Management 20(3): pp. 235–240.

 

Hillson, D.; Fellow, P.M.I. 2014. How to manage the risks you didn’t know you were taking The problem with the typical project risk management approach What is risk ? First principles Different types of ‘mattering’, Project Management Institute, 1–8.

 

Huchzermeier, A.; Loch, C.H. 2001. Project management under risk: Using the real options approach to evaluate flexibility in R&D, Management Science 47(1): 85–101.

 

Jasiukevicius, L.; Vasiliauskaite, A. 2015. Cost overrun risk assessment in the public investment projects: An empirically-grounded research, Engineering Economics 26(3): 245–254.

 

Johansen, A.; Olsson, N.O.E.; George, J.; Rølstadås, A. 2019. Practical Risk and Opportunity Management (Chapter), in Book: Project Risk and Opportunity Management, Routledge. 17 p. Available from Internet: https://doi.org/10.1201/9780429430589-6.

 

Klakegg, O. 2010. Governance of Major Public Investment Projects In Pursuit of Relevance and Sustainability, NTNU. Available from Internet: https://doi.org/ISBN 978-82-471-1986-0.

 

Krane, P.H.; Olsson, N.O.E. 2013. Uncertainty management of projects from the owners’ perspective, with main focus on managing delivered functionality, International Journal of Managing Projects in Business 7(1): 133–143.

 

Kreiner, K. 1995. In search of relevance: Project management in drifting environments, Scandinavian Journal of Management 11(4): 335–346.

 

Love, P.E.D.; Ahiaga-Dagbui, D.D. 2018. Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects, Transportation Research Part A: Policy and Practice 113: 357–368.

 

Membah, J.; Asa, E. 2015. Estimating cost for transportation tunnel projects: A systematic literature review, International Journal of Construction Management 15(3): 196–218.

 

Odeck, J. 2004. Cost overruns in road construction—what are their sizes and determinants?, Transport Policy 11(1): 43–53.

 

Odeck, J.; Welde, M.; Volden, G.H. 2015. The impact of external quality assurance of costs estimates on cost overruns: Empirical evidence from the norwegian road sector, European Journal of Transport and Infrastructure Research 15(3): 286–303.

 

Olsson, N. 2006. Project Flexibility in Large Engineering Projects. Doctoral Thesis. Norwegian University of Science and Technology, Faculty of Engineering Science and Technology, Department of Civil and Transport Engineering. 151 p.

 

Olsson, N.O.E. 2014. title in english. [In provide the language: Bruk av kuttlister i store statlige investeringer]. NTNU‐rapport. 36 p.

 

Olsson, N.O.E. 2015. Implementation of Pre-defined Potential Scope Reductions in Projects, Procedia Computer Science 64(1877): 387–394.

 

Olsson, N.O.E.; Hansen, G.K. 2010. Identification of critical factors affecting flexibility in hospital construction projects, Health Environments Research and Design Journal 3(2): 30–47.

 

Olsson, N.O.E.; Magnussen, O.M. 2007. Flexibility at Different Stages in the Life Cycle of Projects: An Empirical Illustration of the ‘Freedom to Maneuver’, Project Management Journal 38(4): 25–32.

 

Paslawski, J. 2017. Flexible Approach for Construction Process Management under Risk and Uncertainty, Procedia Engineering 208: 114–124.

 

PMBOK. 2013. A Guide to the Project Management Body of Knowledge(PMBOK® Guide). 5th ed.

 

Samset, K.; Volden, G.H. 2013. Concept No.36 Investing for Impact Lessons with the Norwegian State Project Model and the first investment projects that have been subjected to external quality assurance. Concept rapport. Ex Ante Akademisk forlag. 51 p.

 

Samset, K.; Volden, G.H. 2016. Front-end definition of projects: Ten paradoxes and some reflections regarding project management and project governance, International Journal of Project Management 34(2): 297–313.

 

Shahu, R.; Pundir, A.K.; Ganapathy, L. 2012. An empirical study on flexibility: A critical success factor of construction projects, Global Journal of Flexible Systems Management 13(3): 123–128.

 

Torp, O.; Magnussen, O.M.; Olsson, N.O.E.; Klakegg, O.J. 2006. Cost uncertainty in large govermental investment projects. Concept Rapport Nr. 15, NTNU. 95 p.

 

Welde, M.; Odeck, J. 2017. Cost escalations in the front-end of projects–empirical evidence from Norwegian road projects, Transport Reviews 37(5): 612–630.

 

Welde, M. 2018. In search of success: Ex-post evaluation of a Norwegian motorway project, Case Studies on Transport Policy 6(4): 475–482.

 

Welde, M.; Jørgensen, M.; Larssen, P.F.; Halkjelsvik, T. 2019. Estimating costs in large government investment projects. How good are the estimates and uncertainty analyses in the QA2-reports? No. 59. 96 p.